Gravel by project
How much MOT Type 1 for a 10 m2 base?
A sub-base estimate using 10 m2 area, 10 cm depth, and a denser material assumption.
Estimated result
Pre-calculated from the example inputs below. Adjust them in the calculator for your own numbers.
- Volume
- 1 m3 (1.31 yd3)
- Weight
- 2.2 t (2.43 US tons)
- Bag count
- 3 x 850 kg bags
A 10 m2 MOT Type 1 base at 10 cm depth needs the volume, tonnes, and bag count shown below. This is a material quantity estimate only; compacted depth, ground preparation, and drainage need to be confirmed for the actual project.
How to use this project example
This example uses a 10 m2 finished area at 10 cm depth. It estimates 1 m3 before applying density and allowance, so it is best used as a quantity check after the finished area and depth are decided.
- Measure inside the edging line or finished border, not the rough excavation area.
- Keep sub-base, compaction, and drainage decisions separate from decorative gravel coverage.
- Split irregular shapes into sections and add the results together.
Ordering checks
The example uses 2 t/m3 density and 850 kg bags, giving 2.2 tonnes after allowance. Supplier bag weights, moisture, and delivery options can change the practical order.
- Confirm the supplier bulk-bag weight because 800 kg, 850 kg, and tonne bags are not interchangeable.
- Check delivery access and where the aggregate can be dropped.
- Keep a small allowance for edging losses, settlement, and topping up.
10 m2 Type 1 base gravel checks
| Input | Example value | Planning note |
|---|---|---|
| Area | 10 m2 | Finished surface area before depth is applied. |
| Depth | 10 cm | Changing depth changes volume directly. |
| Density | 2 t/m3 | Supplier figures should replace the default where available. |
| Order unit | 850 kg bags | 3 bags in this example after allowance. |
Example inputs used
- Length: 5
- Width: 2
- Depth: 10
- Aggregate density: 2
- Bag size: 850
These are starting values for this example. Measure or confirm your own figures, then open them in the gravel calculator.
Assumptions and limits
- Uses 5 x 2 m as a simple 10 m2 base area.
- Uses 2.0 t/m3 as a planning density for MOT Type 1.
- Uses 850 kg as the bulk bag weight.
- Includes a 10% waste and settling allowance.
This is an estimate. Site conditions, compaction, and aggregate type can change the final quantity.